• CONTRACT AMOUNT: 214,000
  • INDUSTRY:Power/Energy
  • CLIENT:Pacific Steel and Recycling
  • LOCATION:Frenchtown, Montana
  • COMPLETION YEAR: 2018

Northwest Demolition was contracted for the selective removal of a 140’ stack and associated boiler structure at a Montana power plant.  A high-reach excavator was utilized to remove the taller structures and a large pipe rack.  Northwest Demolition also prepared the remaining top-hung boiler for implosion.  The remote nature of the project site required additional logistics coordination.